The Short Answer: How Long Does a Kitchen Renovation Take?
A mid-range kitchen renovation in Ontario typically takes 6–10 weeks from demolition to final walkthrough. Add 3–6 weeks for permit approval before construction begins, and 2–4 weeks for planning, design, and material lead times — and your total project timeline from contract signing to completion is usually 12–20 weeks.
Here’s how that breaks down stage by stage — so you know exactly what to expect at every step of your kitchen renovation in Milton, Oakville, Burlington, or Mississauga.
Complete Kitchen Renovation Timeline: Stage by Stage
| Stage | Duration | What Happens |
|---|---|---|
| Planning & Design | 1–3 weeks | Scope defined, drawings prepared, material selections started |
| Quotes & Contract | 1–2 weeks | Compare contractors, sign contract, pay deposit |
| Material Ordering | 4–8 weeks lead time | Cabinets (4–8 wks), countertops (2–4 wks), appliances (1–6 wks) |
| Permit Application | 3–6 weeks | Submitted by contractor; approved by municipal building dept |
| Demolition | 1–3 days | Cabinets, flooring, drywall, old fixtures removed |
| Rough-In Work | 1–2 weeks | Electrical, plumbing, HVAC rough-in or relocation |
| Rough-In Inspection | 1–5 days wait | Municipal inspector approves rough-in before walls close |
| Drywall & Ceiling | 3–5 days | New drywall hung, taped, mudded, sanded |
| Cabinet Installation | 2–5 days | Base and upper cabinets installed and levelled |
| Countertop Template & Fab | 7–14 days | Fabricator templates after cabinets; stone cut and polished |
| Countertop Installation | 1 day | Slabs delivered and installed |
| Tile Backsplash | 2–4 days | Tile installed, grouted, sealed |
| Flooring | 2–4 days | Hardwood, LVP, or tile installed and finished |
| Appliance Installation | 1–2 days | Range, fridge, dishwasher, microwave installed and tested |
| Plumbing Finish | 1 day | Faucet, sink, dishwasher connections completed |
| Electrical Finish | 1 day | Switches, outlets, lighting, range hood wired |
| Paint & Touch-Ups | 2–3 days | Final coat on walls, trim painted, touch-ups throughout |
| Final Inspection | 1–3 days wait | Municipal final inspection and permit closeout |
| Punch List & Cleanup | 1–2 days | Deficiencies fixed, site cleaned, final walkthrough with client |
Timeline by Project Scope
| Scope | Construction Phase | Total (inc. planning & permits) |
|---|---|---|
| Cosmetic refresh (no plumbing/electrical move) | 3–5 weeks | 6–9 weeks |
| Mid-range renovation (some relocations) | 6–10 weeks | 12–18 weeks |
| Full gut renovation (structural changes) | 8–14 weeks | 14–22 weeks |
| Kitchen + open concept conversion | 10–16 weeks | 16–26 weeks |
What Causes Kitchen Renovation Delays in Ontario?
- Cabinet lead times: Custom cabinets take 6–10 weeks; semi-custom 4–6 weeks. Order before demo day.
- Countertop fabrication: Stone template happens after cabinet install, then 7–14 days to fabricate.
- Permit approvals: Milton, Oakville, Burlington, Mississauga — all 3–6 weeks. Contractor should apply at contract signing.
- Structural discoveries: Old wiring, inadequate panels, or subfloor damage found during demo adds time and cost.
- Appliance availability: Panel-ready and professional-grade appliances can have 4–20 week lead times.
How to Keep Your Renovation on Schedule
- Finalize all design decisions before demo day — every change after construction begins costs time and money.
- Order all materials before demolition begins — cabinets, tile, and countertop slab must be selected.
- Set up a temporary kitchen (microwave, mini fridge, countertop burner) so you’re not dependent on eating out for 8–10 weeks.
- Be available for same-day decisions — 3-day response delays cause week-long bottlenecks.
- Ask your contractor to book inspections proactively — don’t wait until the phase is done to call the inspector.
Book Your Kitchen Renovation in Halton Region
Mila 4 Renovation manages every stage of kitchen renovations across Milton, Oakville, Burlington, and Mississauga — including permits, scheduling, material coordination, and all trades.
📞 Call 647-280-7780 for your free consultation and detailed timeline estimate.
Related: Kitchen Renovation Cost Ontario | Spring Renovation Planning 2027 | Kitchen Renovation Milton